PREORDERS AND GROUPBUYS

PRODUCT UPDATES

GROUPBUYS and preorders

These are estimated to arrive to us Q4 2026.

Production completion estimate is November.

Updated shipping time to vendors is November 2026 and to customers is November/December 2026.

  • Magnets - ready
  • Feet - ready
  • Hardware - ready
  • CNCed parts - in surface treatment
  • PCBs - ready
  • Silicone parts - ready
  • Carrying case - ready
  • Injection molded tops - in production
  • Torx sticks - ready

Housing samples arrived but they were heavily damaged from shipping without sufficient protection. This prevents us from evaluating or testing the housings from the new manu so we have to get another round. We are pushing to try to get the new round made before the end of the month (Oct). 
Estimate will be updated here.

  • PCBs - ready
  • Plates - ready
  • Magnets - ready
  • Feet - ready
  • Housings - delayed
  • Carrying case - ready

These are estimated to arrive to us Q4 2026 which spans October - December.

  • Housings - in production
  • Plates - in production
  • Bumpers - complete
  • Poron strips - complete
  • DynaPaks - complete
  • HE PCBs - on order with Geon
  • Hybrid PCBs - preproduction sample in testing
  • Carrying case - production queue

These are estimated to arrive to us Q4 2026 which spans October - December.

Ktechs is lead vendor on this project - status as of mid-August is in production.

These are estimated to arrive to us Q1 2027 which spans January - March.

These are estimated to arrive to us Q1 2027 which spans January - March.